In order to supply robust system solutions, we pre-test many third-party manufactured HART and Foundation Fieldbus field devices in our system test laboratory for compatibility with our Integrated Architecture-based plant automation system. Each field device is subjected to interoperability testing procedures similar to operating procedures in your plant. The results of each field test are recorded in a test report for integration planning purposes.
As strategic alliance partners, we and Endress+Hauser are collaborating to provide pre-integrated, pre-tested, measurement, automation and information solutions to help reduce integration costs and risks, improve operational efficiency, improve maintenance efficiency, and optimise plant assets. For Endress+Hauser field devices, we take an additional step and provide an 'Interoperability Statement' with each tested instrument.
The Interoperability Statement is assurance that the Endress+Hauser field device satisfactorily meets Integrated Architecture system interoperability performance measures, as jointly established by Rockwell Automation and Endress+Hauser, and verified through completion of common test procedures performed by either party.
Field Device Testing Procedures
- Install the Third Party Device in an operating H1 network.
- Change the BOF Class of the device.
- Assign a tag to the device.
- Add function blocks to device.
- Perform download operations.
- Set device to factory defaults.
- Configure function blocks.
- Export tags.
- Create a Control Module and add function blocks and links to the Linking Device.
- Verify device operation – monitor link values.
- Verify device operation – UPDATE Command.
- Verify that a device can bridge across H1 channels in the same FFLD.
- Verify that a device will operate with the AB CN2FF module.